LEAN TOOLS APPLICATION TO MINIMIZE CONSTRUCTION WASTE AND IMPROVE SITE PRODUCTIVITY: A CASE STUDY ON 5S SYSTEM AND LAST PLANNER SYSTEM

AUTHORS:
Dhruvin Bharania
Mentor
Darshan Shah, Jayraj Solanki, Paresh Patel
Affiliation
Department of Civil Engineering, U.V. Patel College of Engineering, Ganpat University, Kherva, Mehsana
CC BY 4.0 License:
This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Abstract

Persistent challenges in the construction industry include wastage of materials, budget overruns, schedule delays, and low labour productivity, where it is reported that more than 30 percent of construction works are non-value adding activities. The purpose of this research is to examine the performance of two major lean construction practices, namely, 5S System and Last Planner System (LPS), in reducing wastage in construction sites and enhancing productivity for a residential-commercial building project in Ahmedabad, Gujarat. A mixed methodological design approach was employed in this study where a field study was carried out for 15 days and two questionnaires were administered among 82 construction professionals in various designations such as Project Manager, Planning Engineer, Site Engineer, Supervisor, and Contractor. The Relative Importance Index (RII) was used for analysing data collected through this study. The 5S System had an overall RII of 0.869, resulting in an approximate reduction of between 8–12% in material waste and between 10–18% increase in labour efficiency. The Last Planner System was more efficient with an overall RII of 0.890, leading to a reduction of between 12–20% in project delay and between 15–22% increase in productivity. The percent plan complete increased from 60% to 85% after the use of LPS. Some of the major challenges associated with lean implementation include lack of awareness, inadequate training, and lack of acceptance towards change.

Keywords
Article Metrics
Article Views
316
PDF Downloads
4
HOW TO CITE
APA

MLA

Chicago

Copy

Bharania, D. (2026). Lean Tools Application to Minimize Construction Waste and Improve Site Productivity: A Case Study on 5S System and Last Planner System. International Journal of Science, Strategic Management and Technology, 02(05). https://doi.org/10.55041/ijsmt.v2i5.090

Bharania, Dhruvin. "Lean Tools Application to Minimize Construction Waste and Improve Site Productivity: A Case Study on 5S System and Last Planner System." International Journal of Science, Strategic Management and Technology, vol. 02, no. 05, 2026, pp. . doi:https://doi.org/10.55041/ijsmt.v2i5.090.

Bharania, Dhruvin. "Lean Tools Application to Minimize Construction Waste and Improve Site Productivity: A Case Study on 5S System and Last Planner System." International Journal of Science, Strategic Management and Technology 02, no. 05 (2026). https://doi.org/https://doi.org/10.55041/ijsmt.v2i5.090.

References
[1] S. S. Patil, A. K. Gupta, and D. B. Desai, "Analysis of Wastes in Construction Industry with Lean Thinking," International Journal of Engineering Research and Technology, 2013.

[2] Kohar and A. P. Biswas, "Identification of Non-Value Adding Activities using Lean Technology in Construction," IJERT, 2016.

[3] Devaki and Jayanthi, "Barriers to Implementation of Lean Principles in the Indian Construction Industry," IRJET, vol. 1, no. 6, 2014.

[4] S. M. Abdul and A. Fatima, "Analysis of Lean Construction by Using Last Planner System," IJERT, 2014.

[5] A. A. Maru, "Lean Construction in Civil Engineering and Project Management," American Journal of Civil Engineering, vol. 3, no. 3, 2015.

[6] Nifla and Reshma, "Barriers for Implementing Lean Concepts in Indian Construction Industry," IJERT, 2019.

[7] Devakirubai and Naveen, "Waste Minimization in Construction Using Lean Six Sigma," Materials Today: Proceedings, 2021.

[8] R. Raaj and P. Kumar, "Analysis of Lean Construction Practices in Tamil Nadu Construction Industry," IJERT, 2019.

[9] V. Chavan et al., "Work Sampling and Value Stream Mapping of Lean Construction," IRE Journals, 2021.

[10] Yashneil and Shaunak, "Application of Value Stream Mapping to Boost Productivity: A Case Study," IJERT, 2022.
Ethics and Compliance
✓ All ethical standards met
This article has undergone plagiarism screening and double-blind peer review. Editorial policies have been followed. Authors retain copyright under CC BY-NC 4.0 license. The research complies with ethical standards and institutional guidelines.
Indexed In
Similar Articles
Dynamic Ethics of Artificial Intalligence
string(16) "Chaitali Birewar" Birewar, C.
(2026)
DOI: 10.55041/ijsmt.v2i4.098
The Trans-Atlantic Divide at Greenland: “Don-Roe Doctrine” and the Rise of the Age of Colonialism
string(11) "Bhaskar Jha" Jha, B.
(2026)
DOI: 10.55041/ijsmt.v2i4.367
Cyber Crimes Against Women in Digital Spaces: A Critical Analysis of Legal Protection and Emerging Challenges in India
string(17) "Adv. Jyoti Sawant" Sawant, A. J.
(2026)
DOI: 10.55041/ijsmt.v2i5.283
Scroll to Top